7.10.2008
Donechchyna is preparing to Euro-2009/2012
Nowadays, experts of “Traffic building “Altkom” Ltd. company laid 3 kilometres of the lower layer of runway in Donetsk airport. Thus, 75% of task is fulfilled.
All earthworks are coming to an end: installed pipes for light – flash lights, 6 rudder ways are made, frost-resistant roadsides are prepared.
The beginning date of laying upper layer of runway is already known. “Altkom” will begin this strategical period of work in October 9.